Leading When the Plan Breaks. Decisions and Dependable Commitments When Construction Completion Slips
Ask questions that separate explanations. «What is the next production event that has not yet occurred?» «What stops it happening?» «Who can change that condition?» «What information can we inspect?» The answers may reveal a problem the other party has been reluctant to state directly.
This is an inquiry into performance. Avoid diagnosing character where an observable explanation will suffice. If evidence establishes misrepresentation, preserve it and follow the commercial or organisational process.
Inspect the conditions created by the contract
The party asked to promise may not control every relevant risk. The client may retain design decisions, access or approvals while expecting a contractor to provide an unconditional delivery date.
UK Cabinet Office guidance on risk allocation emphasises placing risks with parties reasonably able to manage them and warns of the consequences of inappropriate allocation. This guidance has a defined procurement context; it is not a substitute for interpreting an individual construction agreement. It does offer a useful commercial question: what behaviour does this allocation make likely? [S4]
The answer may include a risk premium, narrow compliance, disputes or reluctant early disclosure. None of those outcomes is inevitable. They should be considered when a promise seems detached from the conditions needed to honour it.
For an existing project, start by establishing the actual agreement and the authorised route for change. A manager should not casually waive obligations, promise payment or alter rights in an attempt to improve a relationship. Better information and properly authorised commercial action belong together.
What Edinburgh shows
The Edinburgh Tram Inquiry identified the infrastructure contract as the principal cause of the project’s delays: its terms led to disputes over interpretation and to work stopping until they were resolved. It recommended that where a business case assumes design, approvals and utility diversions will be complete before the construction contract is awarded, negotiations should wait until they are, or a new business case should be prepared. [S16]
The lesson I take is specific: a commercial label does not establish the state of the dependencies or determine what the full contract does when an assumption changes. A delivery director needs the commercial and legal assessment of that mechanism before relying on the label.
What Priya needed before recommending replacement
The replacement’s envelope drawing looked close enough to encourage optimism. Its interface schedule also listed the required 48 digital inputs, 24 digital outputs, eight analogue channels and two communication links. Matching the counts did not establish that the equipment would behave as the receiving design required.
Priya identified two unresolved items. The existing design and the offered cabinet did not yet show the same division of responsibility for supplying loop power. The proposed communications information also failed to establish the required restart behaviour after a loss of connection. Neither point proved the replacement impossible. Both required a resolved design and supporting evidence before the route could support a handover promise.
Her review separated matters that could be checked from documents from matters requiring demonstration or further design. A vendor’s general statement of equivalence would not close the second group.

By Wednesday’s review, the record still had the loop-supply and restart items open. Ruth could not price the potential site changes accurately, and Ben could not yet confirm whether the quoted factory work supplied all the evidence his site sequence required. The £180,000 offer therefore remained a commercial offer attached to a technically unverified option.
This is the precise uncertainty behind Daniel’s refusal. Whether or not replacement would have worked, the record shows why the apparent three-week recovery and £90,000 advantage had not become an adequately supported recommendation before the offer expired.
Make another week earn its place
Sometimes waiting is the right decision. An investigation may resolve uncertainty cheaply. A supplier’s recovery may become verifiable within hours. The test is whether waiting has a defined information benefit that is worth the options it consumes.
Maya asked Owen what would be known by Wednesday afternoon that was not known on Tuesday. He requested a written production sequence, confirmation of component availability and a named escalation contact. Those were useful outputs. «We will know more next week» was not sufficiently specific when the alternative offer expired this week.
She set a parallel path. The team would continue investigating the original supplier’s recovery while testing the replacement option. This consumed some professional effort, but it protected a choice. It also made clear that parallel investigation was not authority to incur the full replacement cost.
A conversation that tests the promise
Try the following sequence, adapting it to your role.
«What result are you now forecasting, and what does complete mean here?»
«What has changed since the last date?»
«Which necessary conditions are already secured, and which depend on somebody else?»
«What will we be able to verify before the next decision point?»
«What should we do if that evidence does not appear?»
The final question matters. Without it, the group may have an elaborate discussion and return to the same open-ended extension. A fallback can be a further review, a different supplier, a scope decision or an escalation. It must be an action the people in the room can authorise.
When a second reply still contains no evidence
Consider a variation on the first Northbank week that tests the response to a supplier who continues to withhold detail. The main chronology is unchanged.
At Tuesday’s review Owen supplies a recovery slide showing delivery restored to the original date. It has no component-release dates or factory allocation behind it. Asked for those records, he says the supplier will not disclose its production plan to a customer.
Maya narrows the request. She needs confirmation that the critical components are available, that assembly capacity is allocated and that the proposed checks and transport connect to the receiving date. Ruth offers a redacted extract or a call with an authorised production manager. They do not demand unrelated customer information.
By Wednesday morning, the second reply is another slide. Owen says, «They have confirmed it. Asking again will damage the relationship.»
«What did they confirm that I can now use to book installation?» Maya asks. «A named slot and its prerequisites would change the forecast. The repeated date does not.»
She sets the next useful return before the replacement decision window closes. Priya continues the separate compatibility review; Ruth checks what limited reservation, if any, the supplier would really offer and who could authorise it. No reservation is assumed from an unanswered request.
The third reply refuses both the redacted evidence and the production call. Maya stops commissioning versions of the same unanswered enquiry. The recovery claim is recorded as unsupported; the latest evidenced late-delivery position remains the planning basis, with its remaining assumptions stated. The replacement still requires its own technical and commercial decision. Owen’s supply-chain management obligation is not transferred to Maya because she asked the questions.
Her briefing is short: «Original-date recovery remains unverified after two specific evidence requests and an offered confidential route. We cannot release the receiving resources on that promise. The live decisions are the qualified replacement investigation and planning around the supported later route.»
This response does not determine dishonesty, waive a contract or prove the supplier incapable of recovering. Ruth handles any required commercial notice through the actual contract route. The immediate management consequence is narrower: the unsupported claim cannot govern another team’s irreversible action. Further investigation needs new evidence or a new question, not another copy of the request.
I would stop asking whether the supplier is confident at this point. I would ask which commitment I am still being invited to make on its behalf.
The promise and the person
A fourth missed date invites a judgement about the person who gives it. Sometimes that judgement is supported. Sometimes the date conceals a requirement the client has still not supplied. The manager needs a way to distinguish the two without allowing either to become an excuse for endless deferral.
The same review should expose both the changed production basis and the unresolved dependency. The owner of the external condition receives an action just as explicit as the supplier’s. A commitment that depends on a client instruction is reported with that condition visible; it is not quietly presented as unconditional and disputed later.
This approach does not absolve the supplier. It creates a fairer and more useful performance record. If the client answers on time and the supplier still cannot support the date, the next discussion begins from clearer evidence. If the client does not answer, the forecast should show the effect before the date is missed.
Decision practice A date with an unanswered client input
A supplier has missed three dates. It now offers a fourth, conditional on receiving a client configuration decision by noon tomorrow. The client decision is late, but the supplier’s own material availability is also unconfirmed. The sponsor asks you to «hold the supplier to its promise’.
Write the questions and actions you would assign to each party. Explain how you would report the date if the client responds on time but the material position remains unknown.
6 When Disagreement Looks Like Disloyalty
Priya challenged the replacement option before the team had finished discussing its price.
«We are assuming the controls will work with what is already installed,» she said. «I haven’t established that.»
Конец ознакомительного фрагмента.
Текст предоставлен ООО «Литрес».
Прочитайте эту книгу целиком, купив полную легальную версию на Литрес.
Безопасно оплатить книгу можно банковской картой Visa, MasterCard, Maestro, со счета мобильного телефона, с платежного терминала, в салоне МТС или Связной, через PayPal, WebMoney, Яндекс.Деньги, QIWI Кошелек, бонусными картами или другим удобным Вам способом.
Вы ознакомились с фрагментом книги.
Для бесплатного чтения открыта только часть текста.
Приобретайте полный текст книги у нашего партнера:
Полная версия книги
Всего 10 форматов